Timeline
Work package 1: project management
Ensure the timely delivery of all project outputs to the required standard, and keep stakeholders informed throughout the project.
Outputs
- Project plan
- Project blog
- Dissemination of outputs across IHR communication channels
- Final budget and completion report
Work package 2: analysis of public interface
The analysis work package will encompass the first quantitative and qualitative evaluation from the usability / learnability testing exercises and deliver a prioritised list of recommendations to be fed into the build phase.
Outputs
- Task definitions
- Individual user interviews and task observation
- 4 focus groups from workshop held at the IHR
- System usability scale (SUS)
- Remote testing using VerifyApp
- Case study report of usability issues identified
Work package 3: build phase A
Using report from WP2, extend and build new functions which better support users accessing the public query interface
Outputs
- Build prototype solutions to usability issues, which may include
- Modifications to nomenclature and navigation
- Enhancements to statistical tools
- Creation of graphing tool
- Contextual help
- Addition of devices to better reflect temporal or spatial relationships
Work package 4: analysis of administration interface
Focus within this work package will shift towards identifying scholarly editing requirements using quantitative and qualitative techniques and delivering a prioritised list of recommendations to be fed into the subsequent build phase.
Outputs
- Task definitions
- Individual user interviews and task observation
- Focus group held at the IHR
- Remote testing using VerifyApp
- Case study report of usability issues identified
Work package 5: build phase B
Using report from WP4, extend and build new functions which better support editors creating new content and marking up existing data
Outputs
- Build prototype solutions to usability issues, which may include
- Modifications to nomenclature and navigation
- Tools which look at existing patterns of mark up to identify variance
- Permissions and workflow tools
Work package 6: evaluation
Undertake follow-on research to uncover satisfaction with actual / proposed revisions to services.
Outputs
- (Shorter) individual user interviews and task observation
- Interview with selected user from Focus group
- Continued monitoring of SUS
- Repeat remote testing using VerifyApp
- Report drawing together issues and feedback for remedial solutions