Tuesday 19 July 2011

Timeline and work packages



Timeline

Work package 1: project management
Ensure the timely delivery of all project outputs to the required standard, and keep stakeholders informed throughout the project.

Outputs
  • Project plan
  • Project blog
  • Dissemination of outputs across IHR communication channels
  • Final budget and completion report

Work package 2: analysis of public interface
The analysis work package will encompass the first quantitative and qualitative evaluation from the usability / learnability testing exercises and deliver a prioritised list of recommendations to be fed into the build phase.

Outputs
  • Task definitions
  • Individual user interviews and task observation
  • 4 focus groups from workshop held at the IHR
  • System usability scale (SUS)
  • Remote testing using VerifyApp
  • Case study report of usability issues identified

Work package 3: build phase A
Using report from WP2, extend and build new functions which better support users accessing the public query interface

Outputs
  • Build prototype solutions to usability issues, which may include
  • Modifications to nomenclature and navigation
  • Enhancements to statistical tools
  • Creation of graphing tool
  • Contextual help
  • Addition of devices to better reflect temporal or spatial relationships

Work package 4: analysis of administration interface
Focus within this work package will shift towards identifying scholarly editing requirements using quantitative and qualitative techniques and delivering a prioritised list of recommendations to be fed into the subsequent build phase.

Outputs
  • Task definitions
  • Individual user interviews and task observation
  • Focus group held at the IHR
  • Remote testing using VerifyApp
  • Case study report of usability issues identified

Work package 5: build phase B
Using report from WP4, extend and build new functions which better support editors creating new content and marking up existing data

Outputs
  • Build prototype solutions to usability issues, which may include
  • Modifications to nomenclature and navigation
  • Tools which look at existing patterns of mark up to identify variance
  • Permissions and workflow tools

Work package 6: evaluation
Undertake follow-on research to uncover satisfaction with actual / proposed revisions to services.

Outputs
  • (Shorter) individual user interviews and task observation
  • Interview with selected user from Focus group
  • Continued monitoring of SUS
  • Repeat remote testing using VerifyApp
  • Report drawing together issues and feedback for remedial solutions

No comments:

Post a Comment